Wyoming Statutes

§ 29-8-105 — Duration

Wyoming § 29-8-105
JurisdictionWyoming
Title 29Liens
Ch. 8AGRICULTURAL PRODUCER'S LIENS

This text of Wyoming § 29-8-105 (Duration) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyo. Stat. Ann. § 29-8-105 (2026).

Text

(a)A perfected lien created by this act remains in effect until either the lienholder receives the full amount due it for the farm products, including reasonable costs and attorneys' fees incurred in enforcing the lien, or for a period of two hundred ten (210) days from the date the lien becomes perfected as provided in this act.
(b)All actions to foreclose or enforce a lien under this chapter shall be commenced within two hundred forty (240) days after the filing of the lien statement. No lien shall continue to exist except by virtue of the provisions of this chapter for more than two hundred forty (240) days after the lien is filed unless an action to foreclose the lien is instituted.
(c)Whenever any debt which is a lien pursuant to this act is paid and satisfied, the lien claimant sh

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

8
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Wyoming § 29-8-105, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/8/29-8-105.