Wyoming Statutes

§ 41-5-203 — Statement of mechanic's lien; delivery of copy to contractor; time limits for disputing claims; recovery by civil action; application of W.S. 41-5-201 through 41-5-203

Wyoming·Title 41 Water·Ch. 5 IRRIGATION GENERALLY·Art. 2 BONDS AND LIENS FOR LABOR AND MATERIALS
Whenever any verified account mentioned in W.S. 41-5-202 shall be placed in the hands of any such owner or owners or its, his or their agent, as above stated, it shall be the duty of such owner or owners to furnish the contractor with a copy of such verified account, so that if there be any disagreement between the debtor and creditor as to the amount due the same may be amicably adjusted, and if the contractor, or subcontractor if he be the debtor, shall not, within ten (10) days after the receipt of such account, give the said owner or owners or its, his or their agent, written notice that the claim is disputed, he shall be considered as assenting to its payment, and the owner or owners or its, his or their agent, shall be justified in paying the same when due and charging the same to th

Free access — add to your briefcase to read the full text and ask questions with AI

Wyoming § 41-5-203 (Statement of mechanic's lien; delivery of copy to contractor; time limits for disputing claims; recovery by civil action; application of W.S. 41-5-201 through 41-5-203) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

14
View on official source ↗