This text of Wyoming § 41-5-203 (Statement of mechanic's lien; delivery of copy to contractor; time limits for disputing claims; recovery by civil action; application of W.S. 41-5-201 through 41-5-203) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyo. Stat. Ann. § 41-5-203 (2026).

Text

Whenever any verified account mentioned in W.S. 41-5-202 shall be placed in the hands of any such owner or owners or its, his or their agent, as above stated, it shall be the duty of such owner or owners to furnish the contractor with a copy of such verified account, so that if there be any disagreement between the debtor and creditor as to the amount due the same may be amicably adjusted, and if the contractor, or subcontractor if he be the debtor, shall not, within ten (10) days after the receipt of such account, give the said owner or owners or its, his or their agent, written notice that the claim is disputed, he shall be considered as assenting to its payment, and the owner or owners or its, his or their agent, shall be justified in paying the same when due and charging the same to th

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

14
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Wyoming § 41-5-203, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/5/41-5-203.