§ 29-5-105 — Limitation of actions; duration of lien
Wyoming § 29-5-105
This text of Wyoming § 29-5-105 (Limitation of actions; duration of lien) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wyo. Stat. Ann. § 29-5-105 (2026).
Text
Actions for the foreclosure of the lien provided by this chapter
shall be commenced within sixty (60) days from the filing of the
lien statement. No lien continues to exist by virtue of this
chapter for more than sixty (60) days after the lien is filed
unless within that time a civil action is instituted to obtain a
judgment. When any action commences within the sixty (60) days,
the lien continues until the suit is finally determined and
satisfied.
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
7
Cite This Page — Counsel Stack
Bluebook (online)
Wyoming § 29-5-105, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/5/29-5-105.