§ 5D-1-5c — Approval of decommissioning or deconstructing an existing power plant
West Virginia·Ch. 5D PUBLIC ENERGY AUTHORITY ACT·Art. 1 PUBLIC ENERGY AUTHORITY OF THE STATE OF WEST VIRGINIA
(a)No existing coal, oil, or natural gas fueled power plant shall undertake any decommissioning or deconstructing activities prior to obtaining approval from the authority:Provided, That such approval may not be unreasonably withheld.
(b)The authority may approve the decommissioning or deconstructing of an existing coal, oil, or natural gas fueled power plant upon the submission of a petition containing, at a minimum, the following information:
(1)An analysis by an authority approved third party that evaluates the social, environmental, and economic impact at a local and statewide level of such decommissioning and deconstruction; and
(2)Potential alternatives to the decommissioning and deconstruction, including the reconstruction that make use of other technologies, including novel
Free access — add to your briefcase to read the full text and ask questions with AI
West Virginia § 5D-1-5c (Approval of decommissioning or deconstructing an existing power plant) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
2023 Reg. Sess., SB609
Nearby Sections
15
§ 5D-1-1
Short title§ 5D-1-11
Investment of funds by authority§ 5D-1-13
Bonds lawful investments§ 5D-1-14
Exemption from taxation§ 5D-1-18
Transportation fees and other revenues from natural gas transmission projects owned by the authority§ 5D-1-2
Purpose and intent§ 5D-1-22
Liberal construction of article