§ 7006 — Marking of underground utility facilities

Vermont § 7006
JurisdictionVermont
Title 30Title 30: Public Service
Ch. 86Chapter 086: Underground Utility Damage Prevention System

This text of Vermont § 7006 (Marking of underground utility facilities) is published on Counsel Stack Legal Research, covering Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vt. Stat. Ann. tit. 30, § 7006 (2026).

Text

A company notified in accordance with section 7005 of this title shall, within 72 hours, exclusive of Saturdays, Sundays, and legal holidays, after the receipt of the notice, mark the approximate location of its underground utility facilities in the area of the proposed excavation activities; provided, however, if the company advises the person that the proposed excavation area is of such length or size that the company cannot reasonably mark all of the underground utility facilities within 72 hours, the person shall notify the company of the specific locations in which the excavation activities will first occur and the company shall mark facilities in those locations within 72 hours and the remaining facilities within a reasonable time thereafter. A company and an excavator may by agreeme

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

10
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Vermont § 7006, Counsel Stack Legal Research, https://law.counselstack.com/statute/vt/86/7006.