Vermont Statutes

§ 4005 — Retainage

Vermont·Title 9 Title 9: Commerce and Trade·Ch. 102 Chapter 102: Construction Contracts
(a)If payments under a construction contract are subject to retainage, any amounts that have been retained during the performance of the contract and that are due to be released to the contractor upon final completion shall be paid within 30 days after final acceptance of the work.
(b)If an owner is not withholding retainage, a contractor or subcontractor may withhold retainage from its subcontractor in accordance with their agreement. The retainage shall be paid within 30 days after final acceptance of the work.
(c)Notwithstanding any contrary agreement, a contractor shall pay to its subcontractors, and each subcontractor shall in turn pay to its subcontractors, within seven days after receipt of the retainage, the full amount due to each such subcontractor.
(d)If an owner, contractor

Free access — add to your briefcase to read the full text and ask questions with AI

Vermont § 4005 (Retainage) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

10
View on official source ↗