§ 11-13-308 — Effect of failure to comply.
Utah § 11-13-308
JurisdictionUtah
Title 11Cities, Counties, and Local Taxing Units
Ch. 11-13Interlocal Cooperation Act
Part 11-13-3Project Entity Provisions
This text of Utah § 11-13-308 (Effect of failure to comply.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Utah Code Ann. § 11-13-308 (2026).
Text
The construction or operation of a project or of facilities providing additional project capacity may commence and proceed, notwithstanding the fact that all impact alleviation contracts or determination orders with respect to the project or facilities providing additional project capacity have not been entered into or made or that any appeal or review concerning the contract or determination has not been finally resolved. The failure of the project entity or other public agency to comply with the requirements of this chapter or with the terms of any alleviation contract or determination order or any amendment to them may not be grounds for enjoining the construction or operation of the project or facilities providing additional project capacity.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Renumbered and Amended by Chapter 286, 2002 General Session
Nearby Sections
15
§ 11-1-4
Sinking fund -- Investment.§ 11-1-6
Violation of act a misdemeanor.§ 11-10-2
Qualifications of licensee.§ 11-10-3
License fee.§ 11-13-101
Title.§ 11-13-102
Purpose of chapter.§ 11-13-103
Definitions.Cite This Page — Counsel Stack
Bluebook (online)
Utah § 11-13-308, Counsel Stack Legal Research, https://law.counselstack.com/statute/ut/11-13-308.