South Dakota Statutes

§ 34-38-25 — Letter of approval required before proposed construction begins--Letter and plans to be submitted to division.

South Dakota § 34-38-25
JurisdictionSouth Dakota
Title 34PUBLIC HEALTH AND SAFETY
Ch. 34-38FLAMMABLE AND COMBUSTIBLE LIQUIDS

This text of South Dakota § 34-38-25 (Letter of approval required before proposed construction begins--Letter and plans to be submitted to division.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.D. Codified Laws § 34-38-25 (2026).

Text

Before proposed construction begins the applicant shall obtain a letter of approval from the local governing body within whose jurisdiction the system is to be installed. This letter and two sets of plans, blueprints, or drawings shall be submitted to the division for examination and approval of compliance with this chapter.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

SL 1991, ch 269, § 3.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
South Dakota § 34-38-25, Counsel Stack Legal Research, https://law.counselstack.com/statute/sd/34-38-25.