South Carolina Statutes

§ 29-6-50 — Interest on late payments; specific waiver of requirements of sections 29-6-30 and 29-6-50.

South Carolina § 29-6-50
JurisdictionSouth Carolina
Title 29MORTGAGES AND OTHER LIENS
Ch. 6PAYMENTS TO CONTRACTORS, SUBCONTRACTORS, AND SUPPLIERS

This text of South Carolina § 29-6-50 (Interest on late payments; specific waiver of requirements of sections 29-6-30 and 29-6-50.) is published on Counsel Stack Legal Research, covering South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.C. Code Ann. § 29-6-50 (2026).

Text

If a periodic or final payment to a contractor is delayed by more than twenty-one days or if a periodic or final payment to a subcontractor is delayed by more than seven days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor shall pay his contractor or subcontractor interest, beginning on the due date, at the rate of one percent a month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provisions of this section at the time request for payment is made. Nothing in this chapter shall prohibit owners, contractors, and subcontractors, on private construction projects only, from agreeing by contract to rates of inter

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

HISTORY: 1990 Act No. 426, SECTION 1.