§ 29-6-30 — Time and manner of making payment to contractors and subcontractors.
South Carolina·Title 29 MORTGAGES AND OTHER LIENS·Ch. 6 PAYMENTS TO CONTRACTORS, SUBCONTRACTORS, AND SUPPLIERS
When a contractor or a subcontractor has performed in accordance with the provisions of his contract, the owner shall pay the contractor by mailing via first class mail or delivering the undisputed amount of any pay request within twenty-one days of receipt by the owner of any pay request based upon work completed or service provided under the contract, and the contractor shall pay to his subcontractor and each subcontractor shall pay to his subcontractor, within seven days of receipt by the contractor or subcontractor of each periodic or final payment, by mailing via first class mail or delivering the full amount received for that subcontractor's work and materials based on work completed or service provided under the subcontract.
Free access — add to your briefcase to read the full text and ask questions with AI
South Carolina § 29-6-30 (Time and manner of making payment to contractors and subcontractors.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
HISTORY: 1990 Act No. 426, SECTION 1.
Nearby Sections
11
§ 29-6-10
Definitions.§ 29-6-210
Citation of article.§ 29-6-50
Interest on late payments; specific waiver of requirements of sections 29-6-30 and 29-6-50.§ 29-6-60
Application of chapter.