§ 9-1-52 — § 9-1-52. Cause of action for next lowest bidding qualified contractor.
This text of Rhode Island § 9-1-52 (§ 9-1-52. Cause of action for next lowest bidding qualified contractor.) is published on Counsel Stack Legal Research, covering Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Text
§ 9-1-52. Cause of action for next lowest bidding qualified contractor.
Whenever a contractor or subcontractor, having been awarded the contract as the lowest qualified bidder, violates the state's prevailing wage, a cause of action shall be for the next lowest qualified bidder for any and all damages incurred as the result of not being awarded the contract.