Whenever a contractor or subcontractor, having been awarded the contract as the lowest qualified bidder, violates the state's prevailing wage, a cause of action shall be for the next lowest qualified bidder for any and all damages incurred as the result of not being awarded the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Rhode Island § 9-1-52 (§ 9-1-52. Cause of action for next lowest bidding qualified contractor.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

P.L. 1994, ch. 429, § 1.