§ 515 — Construction cost of electric generating units

Pennsylvania·Title 66 PUBLIC UTILITIES·Part PART I·Ch. 5 POWERS AND DUTIES
(a)Submission of estimate.--No later than 30 days after construction of an electric generating unit is begun, either in this Commonwealth or in some other state, any public utility operating in this Commonwealth and owning any share in that unit shall submit to the commission an estimate of the cost of constructing that unit. If the public utility acquires ownership of any share in an electric generating unit which is under construction on the date of acquisition, the public utility shall, within 30 days of the date of acquisition, submit an estimate of the cost of constructing that unit which was formulated no later than 30 days from the beginning of construction.
(b)Auditor in charge.--For each electric generating unit under construction which falls under the provisions of this sectio

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania § 515 (Construction cost of electric generating units) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

(July 6, 1984, P.L.602, No.123, eff. imd.; July 10, 1986, P.L.1238, No.114, eff. imd.) Cross References.Section 515 is referred to in sections 523, 1308 of this title.