Pennsylvania Statutes

§ 1323 — Procedures for new electric generating capacity

Pennsylvania·Title 66 PUBLIC UTILITIES·Part PART I·Ch. 13 RATES AND DISTRIBUTION SYSTEMS·Subch. RATES
(a)Excess capacity costs.--Whenever a public utility claims the costs of an electric generating unit in its rates for the first time and the commission finds that the unit results in the utility having excess capacity, the commission shall disallow from the utility's rates, in the same proportion as found to be excess capacity:
(1)the return on specific unit or units of any excess generating reserve;
(2)the return on the average net original cost per megawatt of the utility's generating capacity; or
(3)the equity investment in the new unit. In addition to the disallowances set forth in this subsection, the commission may disallow any other costs of the unit or units which the commission deems appropriate. For the purposes of this section, a rebuttable presumption is created that a

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania § 1323 (Procedures for new electric generating capacity) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

(July 10, 1986, P.L.1238, No.114, eff. imd.) 1986 Amendment.Act 114 added section 1323. Section 19 of Act 114 provided that section 1323 shall be applicable to all cases pending before the commission.

Nearby Sections

15
View on official source ↗