§ 3932 — Government agency's progress payment obligations
Pennsylvania·Title 62 PROCUREMENT·Part PART II·Ch. 39 CONTRACTS FOR PUBLIC WORKS·Subch. PROMPT PAYMENT SCHEDULES
(a)Payments in accordance with contract.--The government agency shall pay the contractor or design professional strictly in accordance with the contract.
(b)Application for progress payments.--If the contract does not contain a term governing the time for payment, the contractor or design professional shall be entitled to make application for payment from the government agency for progress payments, and the government agency shall make payment less the applicable retainage amount as authorized in section 3921 (relating to retainage) to the contractor or design professional within 45 calendar days of the date the application for payment is received.
(c)Interest on progress payments not timely made.--Except as otherwise agreed by the parties, if any progress payment less the applicable
Free access — add to your briefcase to read the full text and ask questions with AI
Pennsylvania § 3932 (Government agency's progress payment obligations) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Cross References.Section 3932 is referred to in sections 3933, 3938 of this title.