Pennsylvania Statutes

§ 3932 — Government agency's progress payment obligations

Pennsylvania § 3932
JurisdictionPennsylvania
Title 62PROCUREMENT
PartPART II
Ch. 39CONTRACTS FOR PUBLIC WORKS
Subch.PROMPT PAYMENT SCHEDULES

This text of Pennsylvania § 3932 (Government agency's progress payment obligations) is published on Counsel Stack Legal Research, covering Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
62 Pa. Cons. Stat. § 3932 (2026).

Text

(a)Payments in accordance with contract.--The government agency shall pay the contractor or design professional strictly in accordance with the contract.
(b)Application for progress payments.--If the contract does not contain a term governing the time for payment, the contractor or design professional shall be entitled to make application for payment from the government agency for progress payments, and the government agency shall make payment less the applicable retainage amount as authorized in section 3921 (relating to retainage) to the contractor or design professional within 45 calendar days of the date the application for payment is received.
(c)Interest on progress payments not timely made.--Except as otherwise agreed by the parties, if any progress payment less the applicable

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Cross References.Section 3932 is referred to in sections 3933, 3938 of this title.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Pennsylvania § 3932, Counsel Stack Legal Research, https://law.counselstack.com/statute/pa/62/3932.