§ 701.635 — Suspension of performance

Oregon § 701.635
JurisdictionOregon
Vol.17
Title 52Occupations and Professions
Ch. 701Construction Contractors and Contracts

This text of Oregon § 701.635 (Suspension of performance) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 701.635 (2026).

Text

(1)An original contractor may suspend performance under a construction contract, or if performance is suspended for longer than one month may terminate a construction contract, if the owner fails to make timely payment of the amount certified under ORS 701.625. An original contractor shall provide written notice to an owner at least seven days before the original contractor suspends performance or terminates the construction contract, unless a shorter notice period is prescribed in the construction contract. An original contractor may not be deemed in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection. A construction contract may not extend the notice period under this subsection.
(2)A subcontractor may suspend

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 701.625
Oregon § 701.625
§ 701.630
Oregon § 701.630

Legislative History

2003 c.675 §57; 2011 c.553 §4