Oregon Statutes

§ 701.630 — Payments to subcontractors and material suppliers; failure to pay; omission of payment

Oregon § 701.630
JurisdictionOregon
Vol.17
Title 52Occupations and Professions
Ch. 701Construction Contractors and Contracts

This text of Oregon § 701.630 (Payments to subcontractors and material suppliers; failure to pay; omission of payment) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 701.630 (2026).

Text

(1)An original contractor, subcontractor or material supplier that performs in accordance with a construction contract is entitled to payment from the party with whom the original contractor, subcontractor or material supplier contracts.
(2)(a) If a subcontractor has performed in accordance with a construction contract, and the original contractor receives payment from the owner for work performed by the subcontractor, the original contractor shall pay the subcontractor for that work no later than seven days after the original contractor receives the payment. If a material supplier has performed in accordance with a construction contract, and the original contractor receives payment from the owner for materials or products provided by the material supplier, the original contractor shall p

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 701.098
Oregon § 701.098
§ 701.410
Oregon § 701.410

Legislative History

2003 c.675 §56; 2011 c.553 §3