§ 17-286 — Electric utility – Transmission upgrade costs presumed

Oklahoma § 17-286
JurisdictionOklahoma
Title 17Corporation Commission

This text of Oklahoma § 17-286 (Electric utility – Transmission upgrade costs presumed) is published on Counsel Stack Legal Research, covering Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Okla. Stat. tit. 17, § 17-286 (2026).

Text

recoverable – Applications for capital expenditures, facilities. A.

1.The portion of costs incurred by an electric utility, which is subject to rate regulation by the Corporation Commission, for transmission upgrades approved by a regional transmission organization to which the utility is a member and resulting from an order of a federal regulatory authority having legal jurisdiction over interstate regulation of transmission rates, shall be presumed recoverable by the utility. The presumption established in this paragraph may be rebutted by evidence that the costs so incurred by the utility for the transmission upgrades exceed the scope of the project authorized by the regional transmission organization or order issued by the federal regulatory authority having jurisdiction over intersta

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Added by Laws 2005, c. 161, § 1, emerg. eff. May 11, 2005. Amended by Laws 2008, c. 80, § 1, emerg. eff. April 24, 2008; Laws 2008, c. 150, § 1, emerg. eff. May 12, 2008; Laws 2025, c. 216, § 1.