§ 5575.03 — Contract shall not be awarded at more than estimated cost - rejection of bids
Ohio § 5575.03
JurisdictionOhio
Title 55Roads-Highways-Bridges
Ch. 5575Maintenance And Repair - Contract; Force Account
This text of Ohio § 5575.03 (Contract shall not be awarded at more than estimated cost - rejection of bids) is published on Counsel Stack Legal Research, covering Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ohio Rev. Code Ann. § 5575.03 (2026).
Text
No contract for any road improvement shall be awarded at a price more than ten per cent in excess of the estimated cost. The bids received shall be opened at the time stated in the notice. If no bids are made that equal one hundred ten per cent of the estimate or less, the board of township trustees shall either readvertise based upon the original estimate, or request an amended estimate from the county engineer, who shall proceed to make such an estimate as provided in section5575.01of the Revised Code, and proceed to advertise based upon the amended estimate. The board is not required to provide notice of the estimate or amended estimate when readvertising under this section.
No contract shall be awarded for any road improvement without the certification as to funding required under sec
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Effective: September 29, 2017 | Latest Legislation: House Bill 49 - 132nd General Assembly
Nearby Sections
9
§ 5575.04
Bond of contractor§ 5575.06
Donations of labor or material§ 5575.10
Maintenance and repair fundCite This Page — Counsel Stack
Bluebook (online)
Ohio § 5575.03, Counsel Stack Legal Research, https://law.counselstack.com/statute/oh/5575.03.