Except as otherwise provided in NRS 338.595, 338.600 and 338.605:
1.Each subcontractor shall disburse money paid to him or her pursuant to this chapter, including any interest which the subcontractor receives, to his or her subcontractors and suppliers within 10 days after the subcontractor receives the money, in direct proportion to the subcontractors’ and suppliers’ basis in the progress bill or retainage bill and any accrued interest thereon.
2.A subcontractor shall make payments to his or her subcontractor or supplier in an amount equal to that subcontractor’s or supplier’s basis in the payments paid by the contractor to him or her for the supplies, materials and equipment identified in the contract between the contractor and the public body, or in the subcontract between the subcont
Free access — add to your briefcase to read the full text and ask questions with AI
Related
§ 338.595
Nevada § 338.595
Legislative History
(Added to NRS by 1999, 1987 )
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Nevada § 338.590, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.590.