§ 338.595 — Amounts withheld as retainage; payment of interest

Nevada § 338.595
JurisdictionNevada
Title 28PUBLIC WORKS AND PLANNING
Ch. 338Public
Payments Made by Subcontractor to Subcontractors and Suppliers

This text of Nevada § 338.595 (Amounts withheld as retainage; payment of interest) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 338.595 (2026).

Text

1.If a subcontractor and another subcontractor or supplier enter into a subcontract for a public work, the subcontractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.
2.After 50 percent of the work required by the subcontractor or supplier has been performed, the subcontractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the subcontractor, satisfactory progress is being made in the work under the subcontract. The payment must be equal to that paid by the contractor to the subcontractor for the work performed or supplies provided by his or her subc

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 338.600
Nevada § 338.600
§ 338.555
Nevada § 338.555

Legislative History

(Added to NRS by 1999, 1987 ; A 2003, 2449 ; 2011, 1623 ; 2015, 2628 )

Nearby Sections

15
§ 338.010
Definitions
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nevada § 338.595, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.595.