1. If a contractor makes payment to a subcontractor or supplier more than 10 days after the occurrence of any of the following acts or omissions:
(a)The contractor fails to pay his or her subcontractor or supplier in accordance with the provisions of subsection 1 of NRS 338.550 ;
(b)The contractor fails to give his or her subcontractor or supplier the written notice of any withholding as required by subsections 2 and 3 of NRS 338.560 ; or
(c)The contractor receives a subcontractor’s or supplier’s written notice of correction of the condition set forth pursuant to subsection 4 of NRS 338.560 as the reason for the withholding, signed by an authorized agent of the subcontractor or supplier, and fails to:
(1)Pay the amount of the progress payment or retainage payment that was withheld from
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Legislative History
(Added to NRS by 1999, 1986 )
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Nevada § 338.565, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.565.