Nevada Statutes

§ 338.565 — Payment of interest on amounts withheld improperly

Nevada § 338.565
JurisdictionNevada
Title 28PUBLIC WORKS AND PLANNING
Ch. 338Public
Payments Made by Contractor to Subcontractors and Suppliers

This text of Nevada § 338.565 (Payment of interest on amounts withheld improperly) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 338.565 (2026).

Text

1. If a contractor makes payment to a subcontractor or supplier more than 10 days after the occurrence of any of the following acts or omissions:

(a)The contractor fails to pay his or her subcontractor or supplier in accordance with the provisions of subsection 1 of NRS 338.550 ;
(b)The contractor fails to give his or her subcontractor or supplier the written notice of any withholding as required by subsections 2 and 3 of NRS 338.560 ; or
(c)The contractor receives a subcontractor’s or supplier’s written notice of correction of the condition set forth pursuant to subsection 4 of NRS 338.560 as the reason for the withholding, signed by an authorized agent of the subcontractor or supplier, and fails to:
(1)Pay the amount of the progress payment or retainage payment that was withheld from

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 338.550
Nevada § 338.550
§ 338.560
Nevada § 338.560

Legislative History

(Added to NRS by 1999, 1986 )

Nearby Sections

15
§ 338.010
Definitions
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nevada § 338.565, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.565.