Nevada Statutes

§ 338.550 — Time for making payments; amounts paid

Nevada § 338.550
JurisdictionNevada
Title 28PUBLIC WORKS AND PLANNING
Ch. 338Public
Payments Made by Contractor to Subcontractors and Suppliers

This text of Nevada § 338.550 (Time for making payments; amounts paid) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 338.550 (2026).

Text

Except as otherwise provided in NRS 338.555, 338.560 and 338.565:

1.Each contractor shall disburse money paid to the contractor pursuant to this chapter, including any interest which the contractor receives, to his or her subcontractors and suppliers within 10 days after the contractor receives the money, in direct proportion to the subcontractors’ and suppliers’ basis in the progress bill or retainage bill and any accrued interest thereon.
2.A contractor shall make payments to his or her subcontractor or supplier in an amount equal to that subcontractor’s or supplier’s basis in the payments paid by the public body to the contractor for the supplies, material and equipment identified in the contract between the contractor and the public body, or between the subcontractor or supplier and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 338.555
Nevada § 338.555

Legislative History

(Added to NRS by 1987, 559 ; A 1999, 1993 )

Nearby Sections

15
§ 338.010
Definitions
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nevada § 338.550, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.550.