Except as otherwise provided in NRS 338.555, 338.560 and 338.565:
1.Each contractor shall disburse money paid to the contractor pursuant to this chapter, including any interest which the contractor receives, to his or her subcontractors and suppliers within 10 days after the contractor receives the money, in direct proportion to the subcontractors’ and suppliers’ basis in the progress bill or retainage bill and any accrued interest thereon.
2.A contractor shall make payments to his or her subcontractor or supplier in an amount equal to that subcontractor’s or supplier’s basis in the payments paid by the public body to the contractor for the supplies, material and equipment identified in the contract between the contractor and the public body, or between the subcontractor or supplier and
Free access — add to your briefcase to read the full text and ask questions with AI
Related
§ 338.555
Nevada § 338.555
Legislative History
(Added to NRS by 1987, 559 ; A 1999, 1993 )
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Nevada § 338.550, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/338.550.