Text
A.Upon receipt of a claim stated in a stop notice, the construction lender, if any, or the owner, if applicable, shall withhold an amount of construction funds equal to the amount claimed in the stop notice from the original contractor until the claim has been satisfied or adjudicated by a court of competent jurisdiction, unless the remaining construction funds are insufficient to completely satisfy the claim due to the prior disbursement or prior amounts being withheld due to previously received stop notices. In these instances, only the remaining unclaimed portion of the construction loan shall be withheld.
B.All funds not disbursed or unclaimed by a stop notice may be disbursed by the construction lender to the original contractor without liability to the construction lender; provided
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Laws 1989, ch. 301, § 8.
Nearby Sections
15
§ 48-1-1
Federal lien; place of filing§ 48-1-3
Duties of filing officer§ 48-1-4
Repealed§ 48-1-5
Uniformity of interpretation§ 48-1-6
Short title§ 48-10-1
Short title§ 48-10-11
Notice of trustee's sale§ 48-10-14
Payment of bid; trustee's deed§ 48-10-15
Disposition of proceeds of sale§ 48-10-16
RedemptionCite This Page — Counsel Stack
Bluebook (online)
New Mexico § 48-2A-8, Counsel Stack Legal Research, https://law.counselstack.com/statute/nm/48/48-2A-8.