This text of New Mexico § 13-1-124.4 (Construction manager at risk delivery method) is published on Counsel Stack Legal Research, covering New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.M. Stat. Ann. § 13-1-124.4 (2026).

Text

authorized; multiphase selection procedure.

A.A construction manager at risk delivery method may be used when a governing body determines that it is in its interest to use that method on a specific educational facility construction project, provided that the construction manager at risk shall be selected pursuant to the provisions of this section.
B.The governing body shall form a selection committee of at least three members with at least one member being an architect or engineer. The selection committee shall develop an evaluation process, including a multiphase procedure consisting of two or three steps. A two-step procedure may be used when the total amount of money available for the project is less than five hundred thousand dollars ($500,000) and shall include a request for qualifi

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Laws 2007, ch. 141, § 6.