(1)Before the construction manager begins any construction services, the department shall:
(a)Conduct an independent cost estimate for the project; and
(b)Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2)If the construction manager and the department are unable to negotiate a contract, the department may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the department shall be eligible to compete in the other contract procurement processes.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: Laws 2023, LB565, § 15.
Nearby Sections
15
§ 61-101
Transferred to section25-21,270§ 61-102
Transferred to section25-21,271§ 61-103
Transferred to section25-21,272§ 61-104
Transferred to section25-21,273§ 61-105
Transferred to section23-1313§ 61-204
Rules and regulationsCite This Page — Counsel Stack
Bluebook (online)
Nebraska § 61-515, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/61-515.