(1)Before the construction manager begins any construction services, the department shall:
(a)Conduct an independent cost estimate for the project; and
(b)Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2)If the construction manager and the department are unable to negotiate a contract, the department may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the department shall be eligible to compete in the other contract procurement processes.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Source: Laws 2023, LB565, § 15.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nebraska § 61-515, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/61-515.