§ 61-507 — Process for selecting design-builder or progressive design-builder
Nebraska § 61-507
JurisdictionNebraska
Ch. 61Natural Resources
This text of Nebraska § 61-507 (Process for selecting design-builder or progressive design-builder) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 61-507 (2026).
Text
(1)The process for selecting a design-builder and entering into a design-build contract shall be in accordance with sections 61-508 to 61-511 .
(2)Except as otherwise specifically provided in the Public Water and Natural Resources Project Contracting Act, the process for selecting a progressive design-builder and entering into a progressive design-build contract shall be in accordance with sections 61-508 to 61-511 .
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: Laws 2023, LB565, § 7.
Nearby Sections
15
§ 61-101
Transferred to section25-21,270§ 61-102
Transferred to section25-21,271§ 61-103
Transferred to section25-21,272§ 61-104
Transferred to section25-21,273§ 61-105
Transferred to section23-1313§ 61-204
Rules and regulationsCite This Page — Counsel Stack
Bluebook (online)
Nebraska § 61-507, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/61-507.