§ 52-118.02 — Public building construction; bond; action; limitation; person to bring suit; rental equipment, defined
Nebraska § 52-118.02
JurisdictionNebraska
Ch. 52Liens
This text of Nebraska § 52-118.02 (Public building construction; bond; action; limitation; person to bring suit; rental equipment, defined) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 52-118.02 (2026).
Text
Every suit instituted under section 52-118.01 shall be brought by any person entitled to the benefit of this action, but no such suit shall be commenced after the expiration of one year after the date of final settlement of the principal contract. The action shall be in the name of the party claiming the benefits of this action.
For the purposes of subsection (1) of section 52-118 , equipment which is rented for a project covered by such subsection under a lease with an option to purchase shall be considered to be equipment rented under a straight lease agreement not to exceed the reasonable rental value of the equipment during the period such equipment is actually used on such project and unless and until the option to purchase is validly exercised under the contract.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Chicago Lumber Co. v. School District No. 71
417 N.W.2d 757 (Nebraska Supreme Court, 1988)
Legislative History
Source: Laws 1955, c. 199, § 3, p. 567; Laws 1969, c. 435, § 1, p. 1462; Laws 1990, LB 257, § 3.
Annotations: Final settlement under public building contract is a determination made and recorded in accordance with established administrative practice by the officer or department in charge that the contract has been completed and final payment is due. Zimmerman's Electric, Inc. v. Fidelity & Deposit Co., 194 Neb. 248, 231 N.W.2d 342 (1975). Final settlement was made with respect to amount due following completion of the project which was accepted by the owner and action was barred one year thereafter. Boyd v. Benkelman Public Housing Authority, 188 Neb. 69, 195 N.W.2d 230 (1972). Action on bond must be brought within one year after date of final settlement on principal contract. Westinghouse Electric Supply Co. v. Brookley, 176 Neb. 807, 127 N.W.2d 465 (1964).
Nearby Sections
15
§ 52-1001
Federal liens; notice; filing§ 52-1002
Certifications; filing§ 52-1004
Notice; filing; fees; billing§ 52-1006
Act, how construed§ 52-1007
Act, how citedCite This Page — Counsel Stack
Bluebook (online)
Nebraska § 52-118.02, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/52-118.02.