(1)Before the construction manager begins any construction services, a contracting agency shall:
(a)Conduct an independent cost estimate for the project; and
(b)Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2)If the construction manager and the contracting agency are unable to negotiate a contract, the contracting agency may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the contracting agency shall be eligible to compete in the other contract procurement processes.

Free access — add to your briefcase to read the full text and ask questions with AI

Nebraska § 39-2820 (Contracting agency; cost estimate; conduct contract negotiations) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Source: Laws 2016, LB960, § 20; Laws 2019, LB583, § 14.