§ 49-22-07.2 — Waiver of procedures and time schedules
North Dakota § 49-22-07.2
JurisdictionNorth Dakota
Title 49Public Utilities
Ch. 49-22Energy Conversion and Transmission Facility Siting Act
This text of North Dakota § 49-22-07.2 (Waiver of procedures and time schedules) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.D. Cent. Code § 49-22-07.2 (2026).
Text
Any utility which proposes to construct an electric energy conversion facility or an electric
transmission facility within the state may make an application to the commission for a waiver of
any of the procedures or time schedules set forth in this chapter or in the rules adopted
pursuant to this chapter. The commission, upon a finding that the proposed facility is of such
length, design, location, or purpose that it will produce minimal adverse effects, or, upon a
finding that a demonstrable emergency exists, may issue an order waiving specified procedures
and time schedules required by this chapter or by the rules adopted pursuant to this chapter,
including, but not limited to, applications, notices, and hearings, and may forthwith issue a
certificate of site compatibility, a certificate
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 49-01-01
Definitions§ 49-01-03
Oath of public service commissioners§ 49-01-04
Offices of public service commission§ 49-01-05
Salary of commissioners§ 49-01-12
Disposition of penalties§ 49-01-12.1
Public utility fee§ 49-01-13
Biennial reportCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 49-22-07.2, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/49-22-07.2.