1.After carbon dioxide injections into a reservoir end and upon application by the storage operator, the commission shall consider issuing a certificate of project completion.
2.The certificate may only be issued after public notice and hearing. The commission shall establish notice requirements for this hearing.
3.The certificate may only be issued after the commission has consulted with the department of environmental quality.
4.The certificate may not be issued until at least ten years after carbon dioxide injections end.
5.The certificate may only be issued if the storage operator:
a.Is in full compliance with all laws governing the storage facility.
b.Shows that it has addressed all pending claims regarding the storage facility's operation.
c.Shows that the storage reservoir i

Free access — add to your briefcase to read the full text and ask questions with AI

North Dakota § 38-22-17 (Certificate of project completion - Release - Transfer of title and custody) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
View on official source ↗