§ 24-08-03 — Bridges - Supervision, repairs, bids, signs - Liability
1.Each bridge built under the provisions of section 24-08-01 is under the supervision of
the board of county commissioners, and the county shall pay the cost of rebuilding or
repairing these bridges.
2.If the cost of rebuilding or repairing a bridge would exceed two hundred thousand
dollars on estimate of the county engineer and upon the approval of the estimate by
the department, the county commissioners shall advertise for bids and award the
contract pursuant to section 24-08-01. For any contract for a bridge improvement that
exceeds fifty thousand dollars but does not exceed two hundred thousand dollars, the
county, when possible, shall seek quotes from at least two contractors. If a bridge is
destroyed by a flood, fire, or other casualty and the public interest would suffer by the
de
Free access — add to your briefcase to read the full text and ask questions with AI
North Dakota § 24-08-03 (Bridges - Supervision, repairs, bids, signs - Liability) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 24-01-01
Declaration of legislative intent§ 24-01-01.1
Definition of words and phrases§ 24-01-01.2
State highway system - Mileage§ 24-01-02
Designation of state highway system§ 24-01-03
Responsibility for state highway system§ 24-01-03.1
Highway performance classification plan§ 24-01-04.1
Metropolitan planning organizations§ 24-01-06
Authority to abandon sections of routes