North Dakota Statutes
§ 24-08-01 — Construction of bridges by board of county commissioners - Bids - Rejection
Rejection.
If the board of county commissioners approves the construction of a bridge, the county shall
proceed to advertise by publication at least once each week, for two successive weeks, in the
official newspaper of the county, the plans and specifications of the proposed bridge, asking for
sealed bids for the construction of the bridge to be submitted to the board of county
commissioners at the next regular or special meeting of the board, at which time the board shall
proceed to examine all proposals or bids. The first publication for bids must be made at least
fifteen days before the meeting of the board to examine the proposals or bids. Upon the receipt
of satisfactory bids, the board shall award the contract to the lowest responsible bidder,
requiring the bidder to give a bond in
Free access — add to your briefcase to read the full text and ask questions with AI
North Dakota § 24-08-01 (Construction of bridges by board of county commissioners - Bids - Rejection) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 24-01-01
Declaration of legislative intent§ 24-01-01.1
Definition of words and phrases§ 24-01-01.2
State highway system - Mileage§ 24-01-02
Designation of state highway system§ 24-01-03
Responsibility for state highway system§ 24-01-03.1
Highway performance classification plan§ 24-01-04.1
Metropolitan planning organizations§ 24-01-06
Authority to abandon sections of routes