North Dakota Statutes

§ 24-02-25.1 — Claims against project - Notice of claim - When filed - Where filed

North Dakota § 24-02-25.1
JurisdictionNorth Dakota
Title 24Highways, Bridges, and Ferries
Ch. 24-02Director of the Department of Transportation

This text of North Dakota § 24-02-25.1 (Claims against project - Notice of claim - When filed - Where filed) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.D. Cent. Code § 24-02-25.1 (2026).

Text

Any person who has furnished labor, materials, or supplies on a contract awarded under section 24-02-23, and who has not been paid in full at the time of final acceptance of the project by the department, has the right to file a claim against the contractor and the surety furnishing the performance bond. Notice of the claim must be given, in writing, to the contractor or the surety furnishing the performance bond and must provide a clear and concise statement of the labor, materials, and supplies furnished, to whom it was furnished, and the monetary value thereof. The claim must bear interest, on each transaction for labor, materials, or supplies, commencing thirty days after the last transaction. The rate of interest must be the rate provided in section 28-20-34. The notice of the claim

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
North Dakota § 24-02-25.1, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/24-02-25.1.