§ 22C-3 — Time of payment to subcontractors after contractor or other subcontractor has been paid
North Carolina § 22C-3
JurisdictionNorth Carolina
Ch. 22CPayments to Subcontractors
This text of North Carolina § 22C-3 (Time of payment to subcontractors after contractor or other subcontractor has been paid) is published on Counsel Stack Legal Research, covering North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.C. Gen. Stat. § 22C-3 (2026).
Text
When a subcontractor has performed in accordance with the provisions of his contract, the contractor shall pay to his subcontractor and each subcontractor shall pay to his subcontractor, within seven days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor's work and materials based on work completed or service provided under the subcontract. (1987 (Reg. Sess., 1988), c. 946.)
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
6
Cite This Page — Counsel Stack
Bluebook (online)
North Carolina § 22C-3, Counsel Stack Legal Research, https://law.counselstack.com/statute/nc/22C/22C-3.