28-2-2117 . Suspension of performance -- termination.

(1)(a) A contractor may suspend performance under a construction contract for failure by the owner to make timely payment of the amount approved pursuant to 28-2-2103 , and the contractor may terminate the construction contract if the payment obligations are not satisfied within 30 days of suspension.
(b)A contractor shall provide written notice to the owner at least 7 calendar days before the contractor's intended suspension of performance or contract termination unless a shorter notice period is prescribed in the construction contract.
(c)A contractor may not be considered in breach of a construction contract for suspending performance or terminating a construction contract pursuant to this subsection (1).
(d)A construction contra

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 5, Ch. 274, L. 2003.