§ 28-2-2104 — Obligations Upon Delay Of Payment
Montana·Title 28 CONTRACTS AND OTHER OBLIGATIONS·Ch. 2 CONTRACTS·Part 21 Payment of Construction Contractors and Subcontractors
28-2-2104 . Obligations upon delay of payment.
(1)If a periodic or final payment that is required by a construction contract to be paid by an owner to a contractor is delayed by more than 30 days from the date the payment is required by the contract to be made, the owner shall pay to the contractor interest, beginning on the day following the date when the payment is due, at the rate of 1 1/2% a month or a pro rata fraction of that amount on the unpaid balance. If the contractor receives interest from the owner for a delayed payment by the owner, the contractor shall ensure that any interest accrued on a delayed payment is distributed by the contractor to subcontractors on a pro rata basis.
(2)If a periodic or final payment required by a subcontract to be paid by a contractor to a subcon
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 28-2-2104 (Obligations Upon Delay Of Payment) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 6, Ch. 470, L. 1999; amd. Sec. 1, Ch. 244, L. 2005; amd. Sec. 1, Ch. 254, L. 2009.
Nearby Sections
15
§ 28-2-101
Contract Defined§ 28-2-102
Essential Elements Of A Contract§ 28-2-103
Express Versus Implied Contracts§ 28-2-104
Executed Versus Executory Contracts§ 28-2-1601
Alteration Of Oral Contract By Parties§ 28-2-1603
Through 28-2-1610 Reserved§ 28-2-1613
Scope Of Court's Inquiry§ 28-2-1614
Specific Enforcement Of Revised Contract§ 28-2-1701
How Contract Extinguished