§ 28-2-2103 — Payment To Contractor And Subcontractor

Montana § 28-2-2103
JurisdictionMontana
Title 28CONTRACTS AND OTHER OBLIGATIONS
Ch. 2CONTRACTS
Part 21Payment of Construction Contractors and Subcontractors

This text of Montana § 28-2-2103 (Payment To Contractor And Subcontractor) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 28-2-2103 (2026).

Text

28-2-2103 . Payment to contractor and subcontractor.

(1)(a) Except as provided in 28-2-2115 , each construction contract governed by this section must define, within the contract, a monthly billing cycle for the contractor to submit monthly progress payment requests and final payment requests to the owner. The contractor shall submit payment requests to the owner. Payment requests must be based upon actual or estimated work performed and materials supplied during the preceding monthly billing cycle. This requirement does not preclude an owner from mutually agreeing with the contractor to prepay for materials. The owner is considered to have received a payment request when the payment request is submitted to any person designated by the owner in the contract to receive the payment request.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 5, Ch. 470, L. 1999; amd. Sec. 2, Ch. 274, L. 2003.