Subdivision 1.Engineer's report and notice.
When a contract is completed, the engineer shall make a report to the drainage authority showing the contract price, the amount paid on certificates, the unpaid balance, and the work that is completed under the contract. When the report is filed, the auditor shall set a time and location for a hearing on the report. The auditor shall give notice of the hearing by publication or notice by mail at least ten days before the hearing to the owners of affected property. The notice must state that the report is filed, the time and location for the hearing, and that a party objecting to the acceptance of the contract may appear and be heard.
Subd. 2.Hearing.
At the hearing the drainage authority may, by order, direct payment of the balance due if it de
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
1990 c 391 art 5 s 76
Nearby Sections
15
§ 103E.005
DEFINITIONS§ 103E.011
DRAINAGE AUTHORITY POWERS§ 103E.025
PROCEDURE FOR DRAINAGE PROJECT THAT AFFECTS STATE LAND OR WATER AREA USED FOR CONSERVATION§ 103E.035
DEFECTIVE NOTICE§ 103E.043
INFORMAL MEETINGS§ 103E.051
DEFECTIVE PROCEEDINGS§ 103E.061
RIGHT OF ENTRY§ 103E.065
DRAINAGE INSPECTORS§ 103E.071
COUNTY ATTORNEYCite This Page — Counsel Stack
Bluebook (online)
Minnesota § 103E.555, Counsel Stack Legal Research, https://law.counselstack.com/statute/mn/103E/103E.555.