Minnesota Statutes
§ 103E.275 — ENGINEER'S VARIANCE FROM DRAINAGE AUTHORITY ORDER
Minnesota § 103E.275
This text of Minnesota § 103E.275 (ENGINEER'S VARIANCE FROM DRAINAGE AUTHORITY ORDER) is published on Counsel Stack Legal Research, covering Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Minn. Stat. § 103E.275 (2026).
Text
(a)In planning a proposed drainage project, the engineer may vary from the starting point and the line and plan described by the preliminary hearing order if necessary to drain the property likely to be assessed in the proposed drainage project.
(b)The engineer may:
(1)survey and recommend the location of additional necessary ditches and tile;
(2)where better results will be accomplished and more desirable outlets secured, provide for the extension of the outlet; and
(3)provide for different parts of the drainage to flow in different directions with more than one outlet.
(c)The open ditches do not have to connect if they drain the area to be affected in the petition. The variance must be reported with similar information in the detailed survey report.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
1990 c 391 art 5 s 43
Nearby Sections
15
§ 103E.005
DEFINITIONS§ 103E.011
DRAINAGE AUTHORITY POWERS§ 103E.025
PROCEDURE FOR DRAINAGE PROJECT THAT AFFECTS STATE LAND OR WATER AREA USED FOR CONSERVATION§ 103E.035
DEFECTIVE NOTICE§ 103E.043
INFORMAL MEETINGS§ 103E.051
DEFECTIVE PROCEEDINGS§ 103E.061
RIGHT OF ENTRY§ 103E.065
DRAINAGE INSPECTORS§ 103E.071
COUNTY ATTORNEYCite This Page — Counsel Stack
Bluebook (online)
Minnesota § 103E.275, Counsel Stack Legal Research, https://law.counselstack.com/statute/mn/103E/103E.275.