Maine Statutes

§ 38 §635-A — Time limits for processing applications

Maine·Title 38 WATERS AND NAVIGATION·Ch. 5 GENERAL PROVISIONS RELATING TO RIVERS AND STREAMS
Whenever the commissioner receives a properly completed application, the department shall make a decision as expeditiously as possible. When the proposed project lies within the jurisdiction of the Maine Land Use Planning Commission, decisions shall be made within 105 working days except that decisions delegated to the director shall be made within 60 working days. Following one extension of up to 45 working days, the director may waive the time limit requirements of this section only at the request of the applicant.

Free access — add to your briefcase to read the full text and ask questions with AI

Maine § 38 §635-A (Time limits for processing applications) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

PL 1983, c. 779, §4 (NEW). PL 1985, c. 362, §1 (AMD). PL 1989, c. 890, §§A40,B185 (AMD). PL 2011, c. 682, §38 (REV).

Nearby Sections

3
View on official source ↗