Maine Statutes
§ 10 §3253 — Dissolution unless claim filed
Maine·Title 10 COMMERCE AND TRADE·Part 7 LIENS·Ch. 603 BUILDINGS, LOTS, WHARVES AND PIERS; LABOR AND MATERIALS
1.Filing of claim.
The lien under section 3252 is dissolved unless the claimant, within 90 days after ceasing to labor, furnish materials or perform services:
2.Exemption for contract with owner.
This section does not apply when the labor, materials or services are furnished by a contract with the owner of the property affected.
Free access — add to your briefcase to read the full text and ask questions with AI
Maine § 10 §3253 (Dissolution unless claim filed) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
PL 1975, c. 91, §1 (AMD). PL 2005, c. 287, §1 (RPR).
Nearby Sections
15
§ 10 §3201
Labor and materials§ 10 §3251
Lien established§ 10 §3252
Prevention of lien§ 10 §3253
Dissolution unless claim filed§ 10 §3255
Liens preserved and enforced by action§ 10 §3256
Extension of lien§ 10 §3258
Determination of amount; jury trial§ 10 §3260
Deficiency; judgment for balance§ 10 §3262
Enforcement by attachment§ 10 §3263
Petition for release§ 10 §3264
Consolidation of actions