§ 17-108

Maryland·Article gsf State Finance and Procurement·Title 17
(a)Subject to subsection (b) of this section, a supplier may sue on payment security if the supplier:
(1)supplied labor or materials in the prosecution of work provided for in a contract subject to this subtitle; and
(2)has not been paid in full for the labor or materials within 90 days after the day that the person last supplied labor or materials for which the claim is made.
(b)(1) A supplier who has a direct contractual relationship with a subcontractor or sub-subcontractor of a contractor who has provided payment security but no contractual relationship with the contractor may sue on the security if the supplier gives written notice to the contractor within 90 days after the labor or materials for which the claim is made were last supplied in p

Free access — add to your briefcase to read the full text and ask questions with AI

Maryland § 17-108 — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
§ 17-101
§ 17-101
§ 17-102
§ 17-102
§ 17-103
§ 17-103
§ 17-104
§ 17-104
§ 17-105
§ 17-105
§ 17-106
§ 17-106
§ 17-107
§ 17-107
§ 17-108
§ 17-108
§ 17-109
§ 17-109
§ 17-110
§ 17-110
§ 17-111
§ 17-111
§ 17-201
§ 17-201
§ 17-202
§ 17-202
§ 17-204
§ 17-204
§ 17-205
§ 17-205
View on official source ↗