§ 85B — Emergency response plans; submission for review and approval; contents; penalties for failure to file; denial of recovery of service restoration costs for failure to implement emergency response plan

Massachusetts § 85B
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title XXIICORPORATIONS
Ch. 164MANUFACTURE AND SALE OF GAS AND ELECTRICITY

This text of Massachusetts § 85B (Emergency response plans; submission for review and approval; contents; penalties for failure to file; denial of recovery of service restoration costs for failure to implement emergency response plan) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 164, § 85B (2026).

Text

Section 85B.

(a)Each electric distribution, transmission and natural gas distribution company conducting business in the commonwealth shall annually, on or before May 15, submit to the department an emergency response plan for review and approval. The emergency response plan shall be designed for the reasonably prompt restoration of service in the case of an emergency event, which is an event where widespread outages have occurred in the service area of the company due to storms or other causes beyond the control of the company. The emergency response plan shall include, but not be limited to, the following:—
(1)the identification of management staff responsible for company operations during an emergency, the number of service workers who are available to respond to an emergency within 24

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

3
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 85B, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/164/85B.