Text

§2225.2.4. Construction management at risk; public entity A.

(1)Notwithstanding any other provision of law to the contrary, a public entity may use the construction management at risk project delivery method to contract for a project to construct public works as set forth in this Section.
(2)This Section creates an alternative project delivery method, known as "construction management at risk", or "CMAR", for use by a public entity to award a contract to construct public works when deemed in the public interest, beneficial to the owner, and in accordance with the procedures in this Section. The following are reasons to use the CMAR delivery method: collaboration and cost control; concurrent execution of design and construction; a complex project with a tight time frame; owner, designer, a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Legislative History

Acts 2014, No. 782, §1; Acts 2015, No. 163, §1; Acts 2018, No. 456, §1; Acts 2022, No. 573, §1; Acts 2024, No. 725, §1.