§ 66-128f — Monthly financial reports by certain utilities constructing electric generating facilities

Kansas § 66-128f
JurisdictionKansas
Ch. 66PUBLIC UTILITIES
Art. 1POWERS OF STATE CORPORATION COMMISSION

This text of Kansas § 66-128f (Monthly financial reports by certain utilities constructing electric generating facilities) is published on Counsel Stack Legal Research, covering Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kan. Stat. Ann. § 66-128f (2026).

Text

Any public utility subject to the provisions of K.S.A. 66-128b to 66-128g, inclusive, which constructs an electric generating facility and was not required to obtain an advance permit under K.S.A. 66-1,159 et seq. shall make and send monthly financial reports to the state corporation commission. Such reports shall include the following information, as of the date of the report, the:

(a)Actual costs incurred;
(b)total estimated cost of the facility;
(c)percentage of the facility which is actually completed;
(d)estimated date of first commercial operation;
(e)copies of informational filings provided federal agencies having regulatory authority over such construction; and (f) any other information required by the commission. Such reports shall be prepared and certified in the manner and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 66-128b
Kansas § 66-128b
§ 66-1
Kansas § 66-1

Legislative History

L. 1984, ch. 247, § 7; April 19.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Kansas § 66-128f, Counsel Stack Legal Research, https://law.counselstack.com/statute/ks/66-128f.