§ 66-128f — Monthly financial reports by certain utilities constructing electric generating facilities
Any public utility subject to the provisions of K.S.A. 66-128b to 66-128g, inclusive, which constructs an electric generating facility and was not required to obtain an advance permit under K.S.A. 66-1,159 et seq. shall make and send monthly financial reports to the state corporation commission. Such reports shall include the following information, as of the date of the report, the:
(a)Actual costs incurred;
(b)total estimated cost of the facility;
(c)percentage of the facility which is actually completed;
(d)estimated date of first commercial operation;
(e)copies of informational filings provided federal agencies having regulatory authority over such construction; and (f) any other information required by the commission. Such reports shall be prepared and certified in the manner and
Free access — add to your briefcase to read the full text and ask questions with AI
Kansas § 66-128f (Monthly financial reports by certain utilities constructing electric generating facilities) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Legislative History
L. 1984, ch. 247, § 7; April 19.
Nearby Sections
15
§ 66-1,107
Validity of 1925 act§ 66-1,108b
Same; powers of state corporation commission§ 66-1,108c
Same; examination of accounts and records§ 66-1,110
Public motor carriers of property, of household goods or of passengers declared common carriers§ 66-1,112j
Suspension or revocation of permit, certificate or interstate license; notice and hearing§ 66-1,113
Unreasonable charges prohibited