(a)No electric utility shall begin site preparation for or construction of an urban electric transmission line or exercise the right of eminent domain to acquire any interest in land in connection with the site preparation or construction of any such line before such utility has:
(1)Provided notice of the preliminary construction plans to the city in which such urban electric transmission line is proposed to be constructed, and the notice shall:
(A)Be provided at least six months prior to any anticipated construction; and
(B)provide the preliminary construction plans and show the proposed location of all poles and shall provide the dimensions of all poles and supporting facilities relative to existing streets, sight triangles at intersections, easements and public rights-of-way and vis

Free access — add to your briefcase to read the full text and ask questions with AI

Kansas § 66-1,183a (Urban electric transmission lines; siting; notice requirements; definitions) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 66-101a
Kansas § 66-101a
§ 66-104d
Kansas § 66-104d

Legislative History

L. 2021, ch. 25, § 1; July 1.

Nearby Sections

15
View on official source ↗