Kansas Statutes

§ 66-1,183a — Urban electric transmission lines; siting; notice requirements; definitions

Kansas § 66-1,183a
JurisdictionKansas
Ch. 66PUBLIC UTILITIES
Art. 1POWERS OF STATE CORPORATION COMMISSION

This text of Kansas § 66-1,183a (Urban electric transmission lines; siting; notice requirements; definitions) is published on Counsel Stack Legal Research, covering Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kan. Stat. Ann. § 66-1,183a (2026).

Text

(a)No electric utility shall begin site preparation for or construction of an urban electric transmission line or exercise the right of eminent domain to acquire any interest in land in connection with the site preparation or construction of any such line before such utility has:
(1)Provided notice of the preliminary construction plans to the city in which such urban electric transmission line is proposed to be constructed, and the notice shall:
(A)Be provided at least six months prior to any anticipated construction; and
(B)provide the preliminary construction plans and show the proposed location of all poles and shall provide the dimensions of all poles and supporting facilities relative to existing streets, sight triangles at intersections, easements and public rights-of-way and vis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 66-101a
Kansas § 66-101a
§ 66-104d
Kansas § 66-104d

Legislative History

L. 2021, ch. 25, § 1; July 1.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Kansas § 66-1,183a, Counsel Stack Legal Research, https://law.counselstack.com/statute/ks/66-1%2C183a.