Indiana Statutes

§ 32-30-16-8 — Installing new communications infrastructure or making capacity available through existing infrastructure; written notice to property owner required; contents; electricity supplier's plan for making broadband Internet service available; delivery of notice; duty to resend notice; resetting of time period for bringing cause of action; confidential information; no liability for broadband plan

Indiana·Title 32 PROPERTY·Art. 30 CAUSES OF ACTION CONCERNING REAL·Ch. 16 Utility Easements
(a)This section applies to an electricity supplier that:
(1)installs new communications infrastructure; or
(2)makes capacity available for communications service through existing communications infrastructure; within an electric easement under this chapter.
(b)As used in this section, "notice" means a written letter:
(1)that is sent by first class mail by the electricity supplier to the property owner; and
(2)that includes the following information:
(A)The name, address, and telephone number of the electricity supplier, along with a named point of contact for the electricity supplier.
(B)Either:
(i)the address and name associated with the impacted property; or
(ii)if the name of the property owner is not known by the electricity supplier, the address associated with the affected

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 32-30-16-8 (Installing new communications infrastructure or making capacity available through existing infrastructure; written notice to property owner required; contents; electricity supplier's plan for making broadband Internet service available; delivery of notice; duty to resend notice; resetting of time period for bringing cause of action; confidential information; no liability for broadband plan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

As added by P.L.236-2017, SEC.1.

Nearby Sections

15
View on official source ↗