§ 32-30-1-4 — "Date of substantial completion" defined
Indiana·Title 32 PROPERTY·Art. 30 CAUSES OF ACTION CONCERNING REAL·Ch. 1 Statute of Limitations in Actions Concerning Real Estate
As used in this chapter, "date of substantial completion" means the earlier of:
(1)the date upon which construction of an improvement to real
property is sufficiently completed under a contract of
construction, as modified by any additions, deletions, or other
amendments, so that the owner of the real property upon which
the improvement is constructed can occupy and use the premises
in the manner contemplated by the terms of the contract; or
(2)the date of the first beneficial use of the improvement to real
property or of any portion of the improvement.
[Pre-2002 Recodification Citation: 32-15-1-1 part.]
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 32-30-1-4 ("Date of substantial completion" defined) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Sharon Gill, on her own behalf and on behalf of the Estate of Gale Gill v. Evansville Sheet Metal Works, Inc.
970 N.E.2d 633 (Indiana Supreme Court, 2012)
Legislative History
As added by P.L.2-2002, SEC.15.
Nearby Sections
15
§ 32-16-1-1
"Prior property law"§ 32-16-1-2
Purpose of recodification§ 32-16-1-3
Statutory construction of recodification§ 32-16-1-4
Effect of recodification§ 32-16-1-5
Recodification of prior property law§ 32-16-1-6
References to repealed statutes§ 32-16-1-7
References to citations§ 32-16-1-8
References to prior rules§ 32-16-1-9
References to prior property law§ 32-17-1-1
"Grantor"§ 32-17-1-2
Fee simple conveyance§ 32-17-1-3
Estates tail; abolition§ 32-17-1-4
Lineal and collateral warranties; abolition§ 32-17-10-1
Application of chapter