1.If a pipeline right-of-way, or any part of a pipeline right-of-way, is wholly abandoned
for pipeline purposes by the relocation of the pipeline, is not used or operated for a period of
five consecutive years, or if the construction of the pipeline has been commenced and work
has ceased and has not in good faith resumed for five years, the right-of-way may revert as
provided in this section to the person who, at the time of the abandonment or nonuse, is the
owner of the tract from which such right-of-way was taken. For purposes of this section, a
pipeline or a pipeline right-of-way is not considered abandoned or unused if it is transporting
product or is being actively maintained with reasonable anticipation of a future use.
2.To effect a reversion on nonuse of right-of-way, the owner
Free access — add to your briefcase to read the full text and ask questions with AI
1. If a pipeline right-of-way, or any part of a pipeline right-of-way, is wholly abandoned
for pipeline purposes by the relocation of the pipeline, is not used or operated for a period of
five consecutive years, or if the construction of the pipeline has been commenced and work
has ceased and has not in good faith resumed for five years, the right-of-way may revert as
provided in this section to the person who, at the time of the abandonment or nonuse, is the
owner of the tract from which such right-of-way was taken. For purposes of this section, a
pipeline or a pipeline right-of-way is not considered abandoned or unused if it is transporting
product or is being actively maintained with reasonable anticipation of a future use.
2. To effect a reversion on nonuse of right-of-way, the owner or holder of purported fee
title to such real estate shall serve notice upon the owner of such right-of-way easement and,
if filed of record, successors in interest and upon any party in possession of the real estate.
The written notice shall accurately describe the real estate and easement in question, set
out the facts concerning ownership of the fee, ownership of the right-of-way easement, and
the period of abandonment or nonuse, and notify the parties that such reversion shall be
complete and final, and that the easement or other right shall be forfeited, unless the parties
shall, within one hundred twenty days after the completed service of notice, file an affidavit
with the county recorder of the county in which the real estate is located disputing the facts
contained in the notice.
3. The notice shall be served in the same manner as an original notice under the Iowa
rules of civil procedure, except that when notice is served by publication an affidavit shall
not be required before publication. If an affidavit disputing the facts contained in the notice
is not filed within one hundred twenty days, the party serving the notice may file for record
in the office of the county recorder a copy of the notice with proofs of service attached and
endorsed, and when so recorded, the record shall be constructive notice to all persons of the
abandonment, reversion, and forfeiture of such right-of-way.
4. Upon reversion of the easement, the landowner may require the pipeline company to
remove any pipe or pipeline facility remaining on the property. Provisions of this chapter
relating to damages shall apply when the pipeline is removed.
5. Unless otherwise agreed to in writing by the landowner and the pipeline company,
if a pipeline right-of-way is abandoned for pipeline use, but the pipe is not removed from
the right-of-way, the pipeline company shall remain subject to section 479.49, shall remain
responsiblefortheadditionalcostsofsubsequenttilingasprovidedforinsection479.47,shall
mark the location of the line in response to a notice of proposed excavation in accordance
with chapter 480, and shall remain subject to the damage provisions of this chapter in the
event access to or excavation relating to the pipe is required. The landowner shall provide
reasonable access to the pipeline in order to carry out the responsibilities of this subsection.