Florida Statutes
§ 337.141 — Payment of construction or maintenance contracts
Florida § 337.141
This text of Florida § 337.141 (Payment of construction or maintenance contracts) is published on Counsel Stack Legal Research, covering Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Fla. Stat. § 337.141 (2026).
Text
(1)As used in this section, the terms “dispute” or “pending claim” refer to a dispute or pending claim between the prime contractor and the department.
(2)Each contract for construction or maintenance entered into pursuant to this chapter shall provide for final payment within 75 days of final field acceptance, provided all documents which are required by the contract from the contractor, with the exception of the acceptance letter and a consent by the contractor’s surety for release of payment of the retained percentage and final estimate to the contractor, are received within 30 days of final field acceptance. If the contractor fails to provide the documents within 30 days after final field acceptance, payment shall be made within 45 days of receipt by the department of such documents
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
ss. 1, 2, ch. 70-168; s. 1, ch. 77-79; s. 147, ch. 84-309; s. 2, ch. 87-104; s. 1, ch. 88-281; s. 11, ch. 94-239; s. 964, ch. 95-148.
Nearby Sections
15
§ 337.015
Administration of public contracts§ 337.0261
Construction aggregate materials§ 337.107
Contracts for right-of-way services§ 337.1075
Contracts for planning servicesCite This Page — Counsel Stack
Bluebook (online)
Florida § 337.141, Counsel Stack Legal Research, https://law.counselstack.com/statute/fl/337.141.